Greater Manchester
Emergency Lighting
LED Lighting
Load Monitoring
Power Distribution
Greater Manchester
Emergency Lighting
LED Lighting
Load Monitoring
Power Distribution
One Way was appointed to design and deliver the phased upgrade of the LV power distribution infrastructure across a Greater Manchester Combined Authority site. The existing installation included outdated switchgear from the 1940s and 50s—some of which contained asbestos—and lacked accurate documentation. The goal was to create a safe, modern, and compliant electrical system to support current and future operational demands.
The project included a full site survey, load monitoring, design of a new distribution network, and the installation of nine bespoke multi-voltage work bay stations. All works were delivered in a live operational environment with minimal disruption, while also complying with strict CDM and asbestos-handling protocols.